The Formula
Squares = ((perimeter × height + extra area − openings) × (1 + waste)) ÷ 100.
1. Perimeter × average wall height
Measure around the walls being sided and multiply by average wall height. This gives the rectangular bulk of the job. If different elevations have different heights, work them separately and add rather than averaging aggressively.
2. Extra area — gables and dormers
The step most often skipped. A gable is a triangle: area = ½ × base × height, where the base is the wall width and the height is the rise from eave to peak. Add each gable and each dormer face. On a house with two decent gables this is easily a couple of squares that a perimeter-only measurement misses entirely.
3. Opening deductions
Standard rough-opening areas: 21 sq ft per door (a 3×7 ft entry) and 15 sq ft per window (a 3×5 ft unit). A dozen windows is about 180 sq ft — nearly two squares, so it is worth deducting.
Override these for oversized units. A sliding patio door or a big picture window is several times a standard opening; treating it as 15 sq ft over-orders. Count it separately and add its real area to the deduction.
4. Waste factor
10% for straightforward lap siding on simple rectangular walls. Move toward 15% when the elevations are cut up with many openings, when there are multiple gables and dormers needing angled cuts, or when a pattern repeat has to be maintained across seams. Long uninterrupted runs waste less; complex houses waste more, because angled offcuts rarely fit anywhere else.
Worked Example: Simple Ranch
120 ft perimeter, 8 ft walls, no gable area, 1 door, 8 windows, 10% waste:
- Gross wall: 120 × 8 = 960 sq ft
- Openings: (1 × 21) + (8 × 15) = 21 + 120 = 141 sq ft
- Net wall: 960 − 141 = 819 sq ft
- Plus 10% waste: 819 × 1.10 = 900.9 sq ft
- Squares: 900.9 ÷ 100 = 9.01 squares → order 10
Worked Example: Two-Story with Gables
140 ft perimeter, 9 ft average walls, 120 sq ft of gable area, 2 doors, 12 windows, 10% waste:
- Gross wall: (140 × 9) + 120 gable = 1,260 + 120 = 1,380 sq ft
- Openings: (2 × 21) + (12 × 15) = 42 + 180 = 222 sq ft
- Net wall: 1,380 − 222 = 1,158 sq ft
- Plus 10% waste: 1,158 × 1.10 = 1,273.8 sq ft
- Squares: 1,273.8 ÷ 100 = 12.74 squares → order 13
Note the gable contribution: those 120 square feet are 1.2 squares on their own. Omit them and you are more than a full square short, which on a re-side means stopping work to reorder and hoping the dye lot matches.
Ordering Tips
- Round up to whole squares. Siding is sold that way, and being short mid-job is far more expensive than a modest surplus.
- Order all of it at once. Colour varies between production runs. A second order weeks later may not match the first, especially in vinyl.
- Keep a few spares. Existing siding fades, so a replacement bought in five years will not match even if the product still exists. Store spares flat and out of sunlight.
- Count trim separately. Corner posts, J-channel, and starter strip are ordered by linear foot, not by square — see the installation guide for what you need.
Related Guides
- How to Install Lap Siding — Flashing, starter strip, exposure, and fastening
- Siding Types Compared — Pick the material before you price the squares
- What Drives Siding Costs — Turning squares into a budget
Related Calculators
- Siding Calculator — Runs this method with adjustable openings and waste
- Insulation Calculator — While the walls are open
- Gutter Calculator — Usually replaced during a re-side
Written by Daniel McCarney — AceCalc